| Brief Description | Priority |
| Auxiliary Equipment - Stacks & Breaching - Boiler #1 and #2 Renewal | Urgent |
| Exterior Windows - 1978 Construction Renewal | Urgent |
| Hot Water Boilers - Boiler #1 and #2 Renewal | Urgent |
| Roof Coverings - Section B,D,D1,D2,D3,E Renewal | Urgent |
| Auxiliary Equipment - Expansion Tanks - Boiler #1 and #2 Renewal | High |
| B201011 Exterior Walls - Joint Sealant Renewal | High |
| C1030 - Fittings - Washroom - Older Renewal | High |
| C302004 Floor Finishes - Vinyl Tile Renewal | High |
| Cooling Generating Systems - DX Split - CU #1 Renewal | High |
| Distribution Systems - Air Distribution, Heating & Cooling - Duct System - 1978 Renewal | High |
| Elevators and Lifts - Wheelchair Lift Renewal | High |
| Exhaust Systems - Centrifugal Exhaust Fans - 1978 Renewal | High |
| Exterior Doors Renewal | High |
| Exterior Walls - Repairs Renewal | High |
| Fittings - Millwork Renewal | High |
| Floor Finishes - Carpet Renewal | High |
| Floor Finishes - Hardwood Renewal | High |
| Floor Finishes - Sheet vinyl Renewal | High |
| G204010 Site Development - Exterior Stairs - Concrete Exterior Stairs Renewal | High |
| Lighting and Branch Wiring - Exterior Lighting - Pole Mounted Renewal | High |
| Parking Lots - Asphalt Paving Renewal | High |
| Pedestrian Paving - Asphalt Renewal | High |
| Playing Fields - Unpaved Renewal | High |
| Rain Water Drainage Renewal | High |
| Roadways - Original Building Renewal | High |
| Standard Foundations - Repairs Renewal | High |
| Wall Finishes - Painted Renewal | High |
| Air Handling Units - SF #1 and #2 Renewal | Medium |
| Auxiliary Equipment - Chemical Feed Systems Renewal | Medium |
| Auxiliary Equipment - Expansion Tanks - Boiler #3 Renewal | Medium |
| Auxiliary Equipment - HVAC Pumps Renewal | Medium |
| Auxiliary Equipment - Heat Exchanger - Plate Renewal | Medium |
| Auxiliary Equipment - Humidifiers Renewal | Medium |
| Ceiling Finishes - Original Building Renewal | Medium |
| Chilled Water Systems - Air-Cooled Chiller Renewal | Medium |
| Controls & Instrumentation - EMS Renewal | Medium |
| Domestic Water Distribution - Eyewash Station Renewal | Medium |
| Domestic Water Distribution - Pipes and Fittings Renewal | Medium |
| Exhaust Systems - Centrifugal Exhaust Fans - 1997 Renewal | Medium |
| Exterior Doors - Aluminium Renewal | Medium |
| Exterior Doors - Hardware Renewal | Medium |
| Fencing & Gates - Chain Link Fence Renewal | Medium |
| Fittings - Metal - 1998 Construction Renewal | Medium |
| Heated Water Distribution Systems - Pipes and Fittings - 1978 Renewal | Medium |
| Interior Doors - 1978 Construction Renewal | Medium |
| Interior Doors - Hardware - 1978 Construction Renewal | Medium |
| Interior Stair Construction - 3 interior steel framed stairs Renewal | Medium |
| Landscaping Renewal | Medium |
| Lighting and Branch Wiring - Branch Wiring - Cabling, Raceways & Bus Ducts Low Density - 1978 Renewal | Medium |
| Sanitary Waste Renewal | Medium |
| Signage Renewal | Medium |
| Stormwater Management Renewal | Medium |
| Ceiling Finishes - Suspended ceiling panels Renewal | Low |
| Domestic Water Distribution - Drinking Fountains and Coolers Renewal | Low |
| Exterior Doors - Automatic Door Device Renewal | Low |
| Fittings - Window Coverings Renewal | Low |
| Pedestrian Paving - Concrete Renewal | Low |
| Plumbing Fixtures - Bradley Basins Renewal | Low |
| Plumbing Fixtures - Lavatories Renewal | Low |
| Plumbing Fixtures - Urinals Renewal | Low |
| Plumbing Fixtures - Water Closets Renewal | Low |