| Brief Description | Priority |
| Auxiliary Equipment - Expansion Tanks Renewal | Urgent |
| Auxiliary Equipment - HVAC Pumps Renewal | Urgent |
| Auxiliary Equipment - Stacks & Breaching Renewal | Urgent |
| Electrical Service and Distribution - Panel (600, 220, 120 V) Renewal | Urgent |
| Energy Supply System - Natural Gas - Piping Renewal | Urgent |
| Exterior Windows - Original Units - 3rd floor Renewal | Urgent |
| Main Switchboards - Switchgear Renewal | Urgent |
| Site Civil/Mechanical Utilities Renewal | Urgent |
| Air Distribution, Heating & Cooling - Ductwork Renewal | High |
| Auxiliary Equipment - Chemical Feed System Renewal | High |
| Branch Wiring - Cabling, Raceways & Bus Ducts Renewal | High |
| C1010 Partitions - Localized Deficiencies Renewal | High |
| C1030 - Fittings - Washroom Renewal | High |
| C302004 Floor Finishes - Vinyl Tile Renewal | High |
| Ceiling Finishes - Acoustic Tile - Classrooms Renewal | High |
| Controls and Instrumentation - Pneumatic Renewal | High |
| Domestic Water Distribution - Eyewash Stations Renewal | High |
| Domestic Water Distribution - Pipes and Fittings Renewal | High |
| Domestic Water Distribution - Sump Pumps Renewal | High |
| Exhaust Systems Renewal | High |
| Exterior Doors - Hardware Renewal | High |
| Exterior Doors - Metal Renewal | High |
| Exterior Lighting - Wall Mounted Renewal | High |
| Exterior Walls - Joint Sealant Renewal | High |
| Exterior Walls - Masonry Re-pointing Renewal | High |
| Fencing & Gates - Chain Link & Wooden Fence Renewal | High |
| Fin Tube Radiation Units - Perimeter Heating Renewal | High |
| Fittings - Millwork Renewal | High |
| Floor Finishes - Sheet Vinyl Floor - Classrooms Renewal | High |
| Heating Water Distribution Systems - Heating Piping System Renewal | High |
| Landscaping - Planters Renewal | High |
| Lighting and Branch Wiring - Stage Lighting Renewal | High |
| Parking Lots - Original Building Renewal | High |
| Pedestrian Paving - Original Building Renewal | High |
| Playing Fields - Paved Renewal | High |
| Plumbing Fixtures - Bradley Basins Renewal | High |
| Plumbing Fixtures - Lavatories Renewal | High |
| Plumbing Fixtures - Water Closets Renewal | High |
| Sanitary Waste Renewal | High |
| Site Development - Exterior Stairs - Concrete Exterior Stairs Renewal | High |
| Standard Foundations Repairs - Parging repairs Renewal | High |
| Wall Finishes - Painted - Classrooms Renewal | High |
| C101003 Partitions - Moveable - Foldable Partition (Classroom) Renewal | Medium |
| Controls & Instrumentation - EMS Renewal | Medium |
| Controls and Instrumentation - BAS Renewal | Medium |
| Cooling Generating Systems - DX Split - CU #1 and #2 Renewal | Medium |
| Domestic Water Distribution - Drinking Fountains and Coolers Renewal | Medium |
| Exit Lighting and Signs Renewal | Medium |
| Exterior Doors - Overhead and Roll - up Renewal | Medium |
| Interior Doors - Wood Renewal | Medium |
| Interior Doors - Hardware Renewal | Medium |
| Lighting Equipment - Interior Lighting Renewal | Medium |
| Plumbing Fixtures - Urinals Renewal | Medium |
| Stormwater Management Renewal | Medium |