| Brief Description | Priority |
| A101004 Standard Foundations Repairs - Parging repairs - Localized Deficiencies Renewal | Urgent |
| Exterior Walls - Localized Deficiencies Renewal | Urgent |
| Exterior Windows - Original Windows Renewal | Urgent |
| Floor Finishes - Carpet Renewal | Urgent |
| Air Handling Units - AHU HTG S-12 & S-9 Renewal | High |
| Air Handling Units - AHU HTG CLG SF 11 Shop Renewal | High |
| Air Handling Units - AHU HTG CLG SF1 GYM Renewal | High |
| Air Handling Units - AHU HTG CLG SF2 CAF Renewal | High |
| Air Handling Units - AHU HTG S7 Renewal | High |
| Air Handling Units - Classroom Unit -1 - AHU CLG SF10 Renewal | High |
| Air Handling Units - Classroom Unit -2 - AHU CLG Renewal | High |
| Air Handling Units - Original Building - AHU HTG SF-3 ADMIN Renewal | High |
| Air Handling Units - Original Building - AHU HTG SF-5 AUD Renewal | High |
| Auxiliary Equipment - Circulation Pumps Renewal | High |
| B201011 Exterior Walls - Joint Sealant - Older Renewal | High |
| B2030 Exterior Doors - Hollow Metal - Older Renewal | High |
| B203004 Exterior Doors - Overhead and Roll - up - Older Renewal | High |
| B203008 Exterior Doors - Hardware - Older Renewal | High |
| C101003 Partitions - Moveable - Foldable Partition (Classroom) Renewal | High |
| C101003 Partitions - Moveable - Foldable Partition (GYM) Renewal | High |
| C1030 - Fittings - Washroom Renewal | High |
| C103009 Fittings - Millwork - Laboratories Renewal | High |
| C103017 Fittings - Auditorium Seating Renewal | High |
| C302004 Floor Finishes - Vinyl Tile Renewal | High |
| Ceiling Finishes - Acoustic Tile Renewal | High |
| Ceiling Finishes - Paint Renewal | High |
| Controls & Instrumentation - BAS System Renewal | High |
| D101012 Elevators and Lifts - Passenger - Hydraulic Renewal | High |
| D202001 Domestic Water Distribution - Pipes and Fittings Renewal | High |
| D302050 Auxiliary Equipment - Chemical Feed System Renewal | High |
| D304007 Distribution Systems - Exhaust Systems Renewal | High |
| D304008 Air Handling Units Renewal | High |
| D305004 Fin Tube Radiation Units Renewal | High |
| D501005 Electrical Service and Distribution - Panel Renewal | High |
| D502001 Lighting and Branch Wiring - Branch Wiring Renewal | High |
| Fittings - Lockers Renewal | High |
| Fittings - Millwork Renewal | High |
| Floor Finishes - Terrazzo Renewal | High |
| G204072 Playing Fields - Gravel Running Track Renewal | High |
| Hot Water Boilers - Heating Boiler -3 Renewal | High |
| Parking Lots - Paved Renewal | High |
| Partitions - Localized Deficiencies Renewal | High |
| Playing Fields - Asphalt Renewal | High |
| Playing Fields - Soccer/Football Field Renewal | High |
| Roadways - Paved Renewal | High |
| Roof Coverings - Section B,BC1,BC2,CD1 Renewal | High |
| Signage Renewal | High |
| Stormwater Management Renewal | High |
| Wall Finishes - Paint Renewal | High |
| Auxiliary Equipment - Expansion Tanks Renewal | Medium |
| C1020 Interior Doors - Hollow Metal / Wood Single Door Renewal | Medium |
| D2010 Plumbing Fixtures - Bradley Basin Renewal | Medium |
| D201001 Plumbing Fixtures - Water Closets Renewal | Medium |
| D201003 Plumbing Fixtures - Lavatories Renewal | Medium |
| D201006 Domestic Water Distribution - Drinking Fountains and Coolers Renewal | Medium |
| Domestic Water Distribution - Sump & Sewage Pumps Renewal | Medium |
| Interior Doors - Hardware Renewal | Medium |
| Main Switchboards - Main Distribution Panel Renewal | Medium |
| Main Switchboards - Switchgear Renewal | Medium |
| Rain Water Drainage Renewal | Medium |
| Roof Coverings - Section A,A1,A2a,A5,A6,B1,C1,D Renewal | Medium |
| Sanitary Waste Renewal | Medium |
| Secondary - Substation Transformer Renewal | Medium |
| Site Civil/Mechanical Utilities Renewal | Medium |
| Ceiling Finishes - Remaining Finishes Renewal | Low |
| Plumbing Fixtures - Replaced Fixtures Renewal | Low |