| Brief Description | Priority |
| Auxiliary Equipment - Condensate, Vacuum Return, Deaerator and Blowdown Renewal | Urgent |
| Auxiliary Equipment - HVAC Pumps Renewal | Urgent |
| Auxiliary Equipment - Stack & Breaching Renewal | Urgent |
| Exterior Windows Renewal | Urgent |
| Heating/Chilling Water Distribution Systems - Piping Renewal | Urgent |
| Secondary - Transformers Renewal | Urgent |
| Site Civil/Mechanical Utilities Renewal | Urgent |
| Standard Foundations Repairs - Damp proofing Repairs - New Renewal | Urgent |
| Standard Foundations Repairs - Parging repairs Renewal | Urgent |
| Steam Boilers - Boiler #1 and #2 Renewal | Urgent |
| ?G204001 Wrought Iron & Chain Link Fencing Renewal | High |
| Air Distribution, Heating & Cooling Renewal | High |
| Air Handling Units - Cafeteria Supply Fan Renewal | High |
| Auxiliary Equipment - Chemical Feed System Renewal | High |
| Auxiliary Equipment - Heat Exchanger - Shell & Tube Renewal | High |
| Branch Wiring Renewal | High |
| C102007 Interior Doors - Hardware Renewal | High |
| C103001 Fittings - Washroom Partitions - Water Closet Renewal | High |
| C103002 Fittings - Washroom Accessories Renewal | High |
| C103009 Fittings - Millwork - Classrooms Renewal | High |
| C103010 Fittings - Millwork - Laboratories Renewal | High |
| C103017 Fittings - Auditorium Seating Renewal | High |
| C302004 Floor Finishes - Vinyl Tile Renewal | High |
| C302007 Floor Finishes - Painted Sealed Concrete Renewal | High |
| Ceiling Finishes - Suspended 2x4 Panels Renewal | High |
| Controls and Instrumentation - Pneumatic Renewal | High |
| Cooling Generating Systems - Rooftop Condensers - 1989 Renewal | High |
| Distribution Systems - Axial Renewal | High |
| Domestic Water Distribution - Eyewash Stations Renewal | High |
| Domestic Water Distribution - Plumbing Piping System - Remaining Original Renewal | High |
| Exhaust Systems - Centrifugal Renewal | High |
| Exterior Doors - Hardware Renewal | High |
| Exterior Doors Renewal | High |
| Exterior Walls - Masonry Re-pointing Renewal | High |
| Floor Finishes - Carpet Flooring Renewal | High |
| G204010 Site Development - Exterior Stairs - Concrete Exterior Stairs Renewal | High |
| Interior Doors - Hollow Wood Renewal | High |
| Other Heat Generating Systems - RTU's - 1989 Renewal | High |
| Other Special Systems and Devices - Dust Collector Renewal | High |
| Partitions - Localized Deficiencies Renewal | High |
| Pedestrian Paving - Asphalt, Concrete, & Interlocking - Paved Renewal | High |
| Perimeter Heating - Terminal Units Renewal | High |
| Plumbing Fixtures - Bradley Basins Renewal | High |
| Plumbing Fixtures - Lavatories Renewal | High |
| Plumbing Fixtures - Urinals Renewal | High |
| Plumbing Fixtures - Water Closets Renewal | High |
| Plumbing Fixtures - Water Fountains Renewal | High |
| Retaining Walls - Concrete Renewal | High |
| Stormwater Management - Grading & Catch Basins Renewal | High |
| Structural Frame - Concrete Canopy Frame Renewal | High |
| Wall Finishes - Paint Renewal | High |
| Ceiling Finishes - Plaster Ceilings Renewal | Medium |
| Domestic Water Distribution - DHW Plumbing Pumps Renewal | Medium |
| Domestic Water Distribution - Natural Gas DWH Renewal | Medium |
| Fencing & Gates - Site Improvements Renewal | Medium |
| Floor Finishes - Hardwood Renewal | Medium |
| Interior Stair Construction Renewal | Medium |
| Other Heat Generating Systems - RTU's - 1999 Renewal | Medium |
| Playing Fields - Unpaved Renewal | Medium |
| Roof Coverings - Section C1,D2,D4,E,E1,F,F1 Renewal | Medium |
| Signage - Wall Mounted & Metal Stand Renewal | Medium |
| Controls & Instrumentation - EMS Renewal | Low |
| Landscaping - Soft Renewal | Low |